Goregaon-Mulund Link Road (GMLR): Route, Status and Timeline
By Kolte-Patil Team | Last Updated: October 2, 2026
Key Takeaway
The Goregaon-Mulund Link Road (GMLR) is a Brihanmumbai Municipal Corporation (BMC) project to connect the Western Express Highway at Goregaon with the Eastern Express Highway at Mulund. This page c…
The Goregaon-Mulund Link Road (GMLR) is a Brihanmumbai Municipal Corporation (BMC) project to connect the Western Express Highway at Goregaon with the Eastern Express Highway at Mulund. This page covers the route, the tunnel section beneath Sanjay Gandhi National Park, the current status and reported timelines, and Metro Line 7 access on the Goregaon side.
Status information on this page is dated and based on published reports and BMC statements. Targets for individual components have changed before and may change again.
What Is the Goregaon-Mulund Link Road?
The GMLR is a road project being implemented by the BMC. It is meant to connect the Western Express Highway (WEH) at Goregaon with the Eastern Express Highway (EEH) at Mulund, and it includes flyover works on the Goregaon side and a tunnel section beneath Sanjay Gandhi National Park (SGNP).
The Prime Minister laid the foundation stone for the tunnel work on 13 July 2024, according to a Press Information Bureau release from the Government of India.
GMLR Route: Goregaon to Mulund
BMC documents describe the route in three parts:
- Goregaon side: BMC’s budget documents place the starting point of the GMLR in Goregaon East. BMC tender documents describe the existing road on the western side as running from the Western Express Highway to Film City.
- Tunnel section: BMC has described the tunnel works as running from Dadasaheb Phalke Chitranagari (Film City) in Goregaon East to Amar Nagar in Mulund West, beneath Sanjay Gandhi National Park.
- Mulund side: BMC tender documents describe the existing road on the eastern side as running from the Eastern Express Highway to Khindipada junction.
The route description above is based on BMC project and tender documents.
Tunnel Section Through Sanjay Gandhi National Park
The tunnel section passes beneath Sanjay Gandhi National Park, with approaches on the Film City side, according to BMC tender documents. BMC is using tunnel boring machines (TBMs) for the excavation. The first TBM, named Tulsi, had excavated 64 metres beneath the park by 24 September 2026. The second TBM, Vihar, was reported to be 92 per cent assembled on the same date, with excavation scheduled to begin from 22 October 2026 after testing, according to the Free Press Journal, which cited BMC.
Current GMLR Status: October 2026
The status below was reported in late September 2026. Reported milestones are listed separately from targets, which are not guaranteed.
Reported milestones
- The Goregaon-side flyover between Dindoshi Court and Film City is in its final stage. Piers, spans, girders, deck slab and approach roads are reported complete, and finishing work is under way, according to Swarajya on 27 September 2026, which reported a BMC site review on 24 September.
- TBM Tulsi had excavated 64 metres of the tunnel beneath Sanjay Gandhi National Park as of 24 September 2026.
Reported targets, subject to change
- Goregaon-side flyover: BMC is targeting opening to traffic by 15 October 2026, after a load test scheduled for the second week of October.
- Second TBM, Vihar: excavation is scheduled to begin from 22 October 2026, subject to testing.
- Project completion: reports have cited different targets. Swarajya reported in March 2026 that completion had been pushed to 2028, while the Free Press Journal reported in September 2026 a February 2029 target. Neither should be treated as a confirmed opening date for the entire corridor.
Earlier targets have not held. BMC had aimed to open the Goregaon-side flyover by 31 May 2026, according to Swarajya in March 2026, and it had not opened by late September 2026. Check BMC announcements for the current position before relying on any date.
Goregaon-Side Works and Connectivity
The Goregaon-side flyover runs between Dindoshi Court and Film City on the Western Express Highway side. It begins near Dindoshi Court, curves around the Ratnagiri Junction Hotel and descends at Dadasaheb Phalke Chitranagari, according to Swarajya’s report of the BMC site review.
BMC’s 2025-26 budget document also describes a proposed elevated GMLR connector from the Mindspace Malad junction on the Mumbai Coastal Road (North) to the starting point of the GMLR in Goregaon East. The document says this would connect the southern tip and western suburbs of Mumbai with Mulund and Thane.
Metro Line 7 Near the Goregaon Side
Mumbai Metro Line 7 (the Red Line) is an elevated corridor along the Western Express Highway, which is where the Goregaon end of the GMLR is located. MMRDA lists its 13 stations from Gundavali to Ovaripada, and those in this part of Goregaon include Goregaon (East), Aarey and Dindoshi. The MMMOCL website publishes current route maps, timings and fares.
According to MMRDA, the section from Dahisar (East) to Aarey opened on 2 April 2022, and the section from Aarey to Andheri (East), which includes Goregaon (East), opened on 19 January 2023. Check the current Metro route and the exact GMLR access point when planning a connection.
What the GMLR Could Change for East-West Connectivity
The GMLR is intended to add another road connection between Mumbai’s western and eastern suburbs. Its eventual effect on individual journeys will depend on the route, traffic conditions and which sections are operational at the time.
Frequently Asked Questions
What is the Goregaon-Mulund Link Road?
The Goregaon-Mulund Link Road (GMLR) is a Brihanmumbai Municipal Corporation (BMC) project meant to connect the Western Express Highway at Goregaon with the Eastern Express Highway at Mulund. It includes flyover works on the Goregaon side and a tunnel section beneath Sanjay Gandhi National Park.
What is the route of the GMLR?
The GMLR connects the Western Express Highway on the Goregaon side with the Eastern Express Highway on the Mulund side. BMC documents place the starting point in Goregaon East. BMC has described the tunnel works as running from Dadasaheb Phalke Chitranagari (Film City) in Goregaon East to Amar Nagar in Mulund West, beneath Sanjay Gandhi National Park, and BMC tender documents describe the existing road on the Mulund side as running from the Eastern Express Highway to Khindipada junction.
What is the current opening timeline for the GMLR?
BMC is targeting 15 October 2026 for opening the Goregaon-side flyover between Dindoshi Court and Film City, after a load test planned for the second week of October, according to Swarajya on 27 September 2026. Excavation of the second tunnel is scheduled to begin from 22 October 2026, subject to testing, according to the Free Press Journal on 24 September 2026. For the project as a whole, reports have cited different targets: Swarajya reported in March 2026 that completion had been pushed to 2028, while the Free Press Journal reported in September 2026 a February 2029 target. Neither should be treated as a confirmed opening date for the entire corridor, and earlier targets have shifted.
Who is building the GMLR?
The Goregaon-Mulund Link Road is a Brihanmumbai Municipal Corporation (BMC) infrastructure project. The foundation stone for the tunnel work was laid on 13 July 2024, according to a Press Information Bureau release from the Government of India.
Which Metro stations are near the Goregaon end of the GMLR?
Mumbai Metro Line 7 runs along the Western Express Highway on the Goregaon side of the GMLR corridor. Its stations in this part of the corridor include Goregaon (East), Aarey and Dindoshi. Travellers should check the current Metro route and the exact GMLR access point when planning a connection.